The council continues working with the auditor's office on Justice Center bond details; progress reported but nothing final.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.
Impact analysis
About $35,000 combined from county funds for both repairs.
County residents who will use the justice facilities.
Mentions & discussions (4)
Commissioners โ November 2, 2026
Failed compressors on the justice center's rooftop unit will be replaced for $32,742 from jail bond funds.
County Council โ June 9, 2026
Commissioners โ June 1, 2026
Two big-ticket building fixes: a dead HVAC unit in the jail phone room ($12,820) and radio tower repairs ($22,096) โ the tower's broken beacon is a flight-safety issue with the airport nearby.
County Council โ March 10, 2026
The council continues working with the auditor's office on Justice Center bond details; progress reported but nothing final.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Boone County
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.