2026 Asphalt Resurfacing Changes
Summary
A $1.68 million contract will resurface roughly four miles of county roads across several townships this year, already baked into the road budget.
At a glance
- Total mentions
- 5
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 5, 2026.
Impact analysis
Costs $1,681,311.95, already in the annual road program budget.
Drivers on resurfaced county roads in the affected townships.
Mentions & discussions (5)
Commissioners โ October 5, 2026
Three change orders to the county's resurfacing contract add patching and milling work but net out to a lower contract total, with possible INDOT reimbursement for part of it.
Commissioners โ March 9, 2026
A $1.68 million contract will resurface roughly four miles of county roads across several townships this year, already baked into the road budget.
Commissioners โ February 23, 2026
The Commissioners were scheduled to open bids for asphalt resurfacing in various townships โ the project that determines which county roads get a fresh surface this year.
Commissioners โ January 20, 2026
The county is spending roughly $575,000 of 2026 road preservation money on crack sealing about 26 center-lane miles and pavement rejuvenation on about 26.5 miles. Both contracts went to the low bidders from the previous meeting.
Commissioners โ January 6, 2026
Bids were opened for crack sealing and rejuvenating surface treatment on township roads, but no contracts were awarded yet. Low bids came from Howard Companies ($319,450) and Rejuvtec ($372,044.85).
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Boone County
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.