Civic Issues
Topics getting the most attention in Bartholomew County public meetings, ranked by how frequently they are discussed.
14 issues in roads
Highway department progress and overlay
The district needs a new trackloader but the only compliant bid came in at $471,148.56 — about $54,000 over the $417,000 budgeted. The board held off on a decision until May to review the bid.
Community Crossings grant shrinkage
After being shut out of state Community Crossings money (over the wheel tax), the county got a call that $843,500 was found for local roads. Phase one covers about 19.32 miles, with a possible phase two using the $1.5 million the council provided as a backup.
Robert Stewart Bridge repainting funded
The county is chipping in its $423,900 share of leftover SR 46 overpass money to help paint the Robert Stewart Bridge, a project costing over $1 million.
Mowing contractor failure and funding transfer
The county picked a new Indianapolis company to mow roadsides for three years, saving about $130,000 versus the local incumbent's bid. The new firm will have to prove itself, and the county holds a 30-day out clause.
Roadside dumping and sign vandalism
Board members vented about people dumping tractor tires and trash along roadsides, frustrating property owners and cleanup crews. The district discussed who bears responsibility when debris lands on private property.
Sidewalk request near outlet mall and formal TIF project process
A company near the outlet mall asked about TIF help building sidewalks for bus riders, but drainage ditches make the proposed spot impractical, and safety concerns remain along the corridors near hotels and restaurants. The commission wants a formal, written application process before considering any request.
Highway 31 interchange improvements at Speedway
The highway engineer is ready to advertise bidding for improvement work near Highway 31 and Speedway, with the RDC contributing $500,000 alongside force construction and the commissioners. Right-of-way issues with Speedway appear resolved.
Oakwood Estates right-of-way dedication
A new 1.6-acre lot on Legal Tender Road came with a required dedication of about a quarter-acre of right-of-way near a curve, with road improvements already finished.
Tally Road bridge cooperative agreement
The county owns every bridge in the county, even inside city limits, so it's chipping in its 20% local share for the Tally Road bridge inspection as part of Columbus's big road widening project.
Bridge project wetland mitigation fee
Because the bridge project footprint disturbs non-wetland floodway forest, the county must buy $77,920 in wetland bank credits — it has no practical alternative under DNR rules.
Tannehill Bridge replacement impact on Newton Park
The bridge project will take a sliver of the curve on the hill up to the bridge, but the surveyor's office says the park won't be negatively impacted.
Lowell Bridge replacement and roundabout project
The Bridge No. 170 replacement over the Driftwood River and a new roundabout at Lowell Road and 325 West are moving forward, with construction inspection now under contract. Bidding happens in January, so construction is still a ways off.
Guardrail Repairs
Someone smashed the guardrails on two 400 West bridges that were just fixed a couple of years ago. With no driver identified, taxpayers cover the $8,400 repair, and the county plans to set the new rails farther from the road.
County road culvert replacements
Three big culverts in southwest Bartholomew County are being replaced this summer, improving drainage and road safety on 700 West, Deaver Road, and 550 South.