Jail rooftop HVAC failure and replacement
Summary
The courthouse cooling tower, in service for decades, had built up impurities that were clogging building units. A $5,188 full system flush by Circle R Mechanical was ratified.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 28, 2026.
Impact analysis
$5,188 from the maintenance budget.
County employees and visitors who rely on the building's HVAC system.
Mentions & discussions (3)
Commissioners โ September 28, 2026
The rooftop unit over the jail kitchen failed about a month and a half ago and wasn't under warranty, so taxpayers covered a $46,918 replacement from EDIT funds.
Commissioners โ July 13, 2026
The jail's four original air units use R-22 coolant that's no longer made, making them unfixable. Commissioners approved $142,106.29 in replacements to be installed in mid-August.
Commissioners โ May 11, 2026
The courthouse cooling tower, in service for decades, had built up impurities that were clogging building units. A $5,188 full system flush by Circle R Mechanical was ratified.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bartholomew County
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.