Final ARP reallocation — water/sewer and ambulance service
Summary
The county still has $4 million in pandemic relief money reserved for broadband, and only about half the county has gotten high-speed internet so far. The money must be spent by year's end, and the county is asking Congressman Shreve's office about an extension.
At a glance
- Total mentions
- 6
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 5, 2026.
Impact analysis
$4 million must be spent or lost by the end of 2026.
Rural households still lacking high-speed internet.
Taxpayers, who absorb the gap between ambulance billings and collections.
Mentions & discussions (6)
Commissioners — October 5, 2026
The county is closing out its American Rescue Plan with $2.5 million going to better water and sewer for the Northern Gateway project and $1.5 million to a joint ambulance service effort with the city and CRH — scrapping the earlier broadband plan.
Commissioners — August 31, 2026
The broadband contractor's bankruptcy left the county at risk of returning $4 million in COVID relief money. A new federal rule allowed reclassifying it to ambulance service and the Taylorsville water project instead.
Commissioners — July 13, 2026
The county still has $4 million in American Rescue Plan money designated for broadband and nothing spent, with a hard deadline at the end of 2026.
Commissioners — April 27, 2026
Commissioners flagged that the county's subsidy for ambulance service is approaching $1 million this year, matched by the city and Columbus Regional. Only about $5 million of nearly $20 million in annual ambulance billings is collected, with 82% of runs Medicare or Medicaid. Residents were reminded each ambulance run costs about $1,500.
Commissioners — April 20, 2026
The county still has $4 million in pandemic relief money reserved for broadband, and only about half the county has gotten high-speed internet so far. The money must be spent by year's end, and the county is asking Congressman Shreve's office about an extension.
Commissioners — February 2, 2026
The county still has $4 million allocated for broadband that hasn't been touched, with no spending in 2025 and the ARPA deadline approaching.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bartholomew County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.