Drainage project change order policy
Summary
A stone-cost overrun on a recent project exposed that the drainage board had no written threshold for change orders. The board set a 20% limit on materials and delivery so work isn't delayed waiting for the next board meeting.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 9, 2026.
Impact analysis
Contract costs can now rise up to 20% on materials without a board vote, which speeds work but means less board oversight of spending.
Taxpayers get projects finished without costly delays, and contractors aren't stuck waiting weeks mid-job.