DC Elliott Drain Phase Two reconstruction
Summary
Phase 1 was done six to eight years ago; Phase 2 is estimated around $50,000 and is the only remaining reconstruction the drain fund can afford. It's now at the top of the list with plans and bidding targeted for this fall.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Sep 14, 2026.
Impact analysis
Estimated around $50,000.
Landowners in the DC Elliott watershed get a functioning tile system.
Watershed landowners who will bear the assessment costs.
Mentions & discussions (4)
Drainage Board — September 14, 2026
A 1913-era tile line serving about 403 acres is being replaced with 2,300 feet of 15-inch tile. Landowners will pay $150 an acre and $450 per lot, down from earlier estimates, and no one objected.
Drainage Board — July 13, 2026
The county plans to rebuild the second branch of the Elliott drain, upsizing tile to 15 inches for about $70,000. Landowners in the watershed would pay roughly $175 per acre or $525 per lot one time — a public hearing is set for September 14.
Drainage Board — June 8, 2026
Tile prices have jumped about 40% since the last meeting, adding roughly $10,000 to the phase-two reconstruction, but the board decided to move ahead rather than gamble on prices falling.
Drainage Board — March 9, 2026
Phase 1 was done six to eight years ago; Phase 2 is estimated around $50,000 and is the only remaining reconstruction the drain fund can afford. It's now at the top of the list with plans and bidding targeted for this fall.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bartholomew County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.