A roughly $31 million commercial building permit was issued for a first-in-Indiana facility that will turn wastewater solids into benign pellets, cutting truck trips to the landfill and saving the city money.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 24, 2026.
Impact analysis
About $31 million in private/utility construction; expected long-term savings for the city utility.
Columbus utility ratepayers through reduced disposal costs and fewer truck trips.
Mentions & discussions (2)
Solid Waste Management — September 24, 2026
City Utilities is installing a dryer at its wastewater plant — possibly the first public utility in Indiana to do so — cutting biosolid volume by roughly 80%. The district landfill could serve as a backup disposal site, and the dried material passed all testing specs.
Commissioners — June 8, 2026
A roughly $31 million commercial building permit was issued for a first-in-Indiana facility that will turn wastewater solids into benign pellets, cutting truck trips to the landfill and saving the city money.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bartholomew County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.