Chuck Wells is pushing to replace the primitive pit toilets at Anderson Falls with a proper modern restroom, asking for cost estimates now rather than waiting for the master plan.
At a glance
- Total mentions
- 5
- Last 30 days
- 0
Last discussed Aug 6, 2026.
Impact analysis
No cost figure yet โ the board wants estimates in hand for budget planning.
Visitors to Anderson Falls who currently use an open-pit toilet facility.
Parkgoers wait at least two more years for restroom improvements.
Mentions & discussions (5)
Park Board โ August 6, 2026
The board sees a pedestrian bridge across the falls to reach 40 acres of unused parkland as a top-three priority โ but it faces big engineering, environmental (DNR), and cost hurdles, likely needing grants.
Park Board โ July 9, 2026
Dennis plans to pursue a grant in 2027 that could cover restroom upgrades at both Anderson Falls and Heflen Park in one application.
Park Board โ June 4, 2026
A 50/50 grant for new precast concrete restrooms at Anderson Falls can't be completed by the June 30 deadline โ public meetings and site requirements take too long. It's now a goal for 2028, with the master plan ready to support the application.
Park Board โ May 7, 2026
The board wants to replace the aging Anderson Falls restrooms using a 50/50 matching DNR grant, which requires county council approval and a cost estimate. Code enforcement is being consulted early.
Park Board โ February 5, 2026
Chuck Wells is pushing to replace the primitive pit toilets at Anderson Falls with a proper modern restroom, asking for cost estimates now rather than waiting for the master plan.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bartholomew County
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.