Civic Center construction progress
Summary
The joint town-school Civic Center is 46% complete, on budget at $36M, and on track to open in November. Contingency spending (~$300K of $3.3M used) and the entry mural design are the open items.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Mar 12, 2026.
Impact analysis
On budget at $36 million total ($20M town, $16M school), with ~$3M contingency remaining.