Critical PriorityGeneralopen

Justice Center project

Summary

The twin courthouse projects keep moving: a revised contract needs to be split into two before commissioners can act, Wiigan's cost estimate arrives at the November 18 budget meeting, asbestos retesting happens this week, and decisions loom on where the clerk's office and courts go during construction.

At a glance

Total mentions
34
Last 30 days
6

Rising — discussed at 9 meetings since Sep 22, 2026, up from 6 in the two months before.

Impact analysis

💰Financial impact

The full cost estimate lands November 18 — expect the number to move as items get value-engineered out.

✅Who benefits

Court users and county staff will eventually get modern, secure judicial facilities.

⚠️Who could be affected

Commissioner Stan Stoppenhagen expressed concern the entrance design may not complement the historic courthouse.

Mentions & discussions (35)

MeetingNov 17, 2026approved

Board of Commissioners - Nov 17, 2026

Wigand construction manager contracts for both the courthouse remodel and Justice Center annex were approved pending legal review. Big open questions include who runs IT cabling, how security equipment is purchased, and furniture budgets — decisions that shape the project for years.

MeetingNov 10, 2026

Board of Commissioners - Nov 10, 2026

The twin courthouse projects keep moving: a revised contract needs to be split into two before commissioners can act, Wiigan's cost estimate arrives at the November 18 budget meeting, asbestos retesting happens this week, and decisions loom on where the clerk's office and courts go during construction.

MeetingNov 10, 2026discussed

County Council - Nov 10, 2026

The county is planning how to pay for the Justice Center: about $7.85 million in cash for courthouse renovations and roughly $14 million in bonds for the Justice Center. Adding another $2 million in cash could save about $170,000 a year on the payment. Firmer construction cost estimates are expected at the December meeting.

MeetingNov 4, 2026

Board of Commissioners - Nov 4, 2026

Commissioners signed off on a revised, plaza-style east entrance to the courthouse and released the schematic design, keeping the judicial center project on schedule. A Weigand Construction cost estimate is due in about two weeks — the first project pricing in roughly three months.

MeetingOct 27, 2026

Board of Commissioners - Oct 27, 2026

Schematic design is accepted (conditionally), the BZA hearing moved to November 17, and a quitclaim deed will combine two parcels for construction. The contract with the construction manager could come to the board November 3.

MeetingOct 20, 2026

Board of Commissioners - Oct 20, 2026

The county paid $700 in review fees to the City of Decatur, will mail certified notices to adjacent property owners, and expects a BZA/planning hearing November 3 or 17. Construction manager Wigand is attending weekly design meetings, with a goal of getting the building under roof before next winter.

MeetingOct 13, 2026

County Council - Oct 13, 2026

The first public look at drawings for the courthouse renovation and a new justice center annex downtown. The project — driven by court security requirements — will cost about $21.3 million combined and bring roughly 18 months of disruption downtown, including two elections during construction.

MeetingOct 13, 2026

Board of Commissioners - Oct 13, 2026

After reviewing seven contractors, the evaluation committee picked Weigand Construction of Fort Wayne as construction manager for the new judicial center. Design is moving too — schematic design is nearly done and a redesigned basement entrance could simplify plumbing.

MeetingOct 6, 2026

Board of Commissioners - Oct 6, 2026

Site investigation work is done, the design-build evaluation committee scores proposals this afternoon, and the county locked in an MOU with Decatur for 35+ court parking spaces. Design renderings go to council next week.

MeetingSep 29, 2026

Board of Commissioners - Sep 29, 2026

Seven qualified contractors applied to build the new judicial center — more than the four or five hoped for. A committee will score and interview the top firms with a recommendation due by November.

MeetingSep 22, 2026

Board of Commissioners - Sep 22, 2026

The county signed architectural agreements for both the new judicial center annex and the courthouse renovation. A parking question before the BZA keeps the annex site flexible, and drilling starts September 30.

MeetingSep 15, 2026

Board of Commissioners - Sep 15, 2026

No action items this week, but the construction manager at-risk RFQ is out with 12 firms engaged, questions due September 21 and packages due September 28; IT space and courthouse connectivity are being worked out.

MeetingSep 8, 2026

County Council - Sep 8, 2026

The Justice Center is moving forward with an owner's rep, contractor bids going out, and courthouse modeling underway. Council members want tight contract language to avoid change orders and overruns on a roughly $20 million-plus project.

MeetingSep 1, 2026

Board of Commissioners - Sep 1, 2026

The judicial center project is moving: two soil-testing bids received, seven construction manager firms contacted for the at-risk RFQ/RFP, and a recommendation expected by October 13.

MeetingAug 18, 2026

Board of Commissioners - Aug 18, 2026

The $20M-plus justice center is moving into early-stage spending: soil testing, surveys, and an architect contract under negotiation. Commissioners are working out how to pre-fund these costs with County Council without missing the September 8 appropriation window.

MeetingAug 11, 2026

County Council - Aug 11, 2026

Designers are meeting with the judges to finalize floor plans, a contract with Elevatus is being negotiated, and the city's promised parking support is being put in writing via an MOU.

MeetingJul 28, 2026

Board of Commissioners - Jul 28, 2026

Commissioners weighed design-bid-build, construction manager options and build-operate-transfer, leaning toward a construction manager at risk with a guaranteed maximum price. They voted to post an owner's rep for seven days, partly because Sheriff Mawhorr cited costly mistakes from the old jail build.

MeetingJul 21, 2026

Board of Commissioners - Jul 21, 2026

The courthouse renovation and new judicial center move forward — commissioners need to pick a construction delivery method soon (CM at-risk is the leading option), decide on one contract or two, and plan an executive session on delivery methods. Design could take 8–10 months once authorized.

MeetingJul 14, 2026discussed

County Council - Jul 14, 2026

The county will renovate the historic courthouse for both courts and build a new annex downtown for the prosecutor, clerk, probation, community corrections and public defender. Council plans to pay about half in cash and borrow the rest, aiming for no tax increase — and members warned they expect tax cuts to continue despite the project. Expect design through 2026, construction starting spring 2027 and finishing by end of 2028.

MeetingJul 14, 2026

Board of Commissioners - Jul 14, 2026

With council funding approved, commissioners mapped out what comes next: meeting the general contractor, locking in department head floor plans, handling zoning and a city agreement, and eventually a public meeting with renderings.

MeetingJul 7, 2026

Board of Commissioners - Jul 7, 2026

The downtown justice center project moved a step forward — the library offered its parking lot to support the project, and the construction contractor estimates a spring 2027 start with about 18 months to build. Commissioners will pitch the project to the County Council next week, which is the key decision point.

MeetingJun 30, 2026

Board of Commissioners - Jun 30, 2026

The commissioners are backing a plan to build a new $20-22 million building for the Clerk, Prosecutor, Probation, Community Corrections and Public Defender, then move the Superior Court into the historic courthouse's first floor. County Council decides July 14 whether to fund it, and is exploring doing so with little to no tax increase.

MeetingJun 23, 2026

Board of Commissioners - Jun 23, 2026

The proposed plan would put Superior Court in the historic courthouse and build a new annex across Third Street for prosecutor, clerk, probation, community corrections and public defender. Total cost is estimated at $20-$22.5 million, and commissioners want to pitch it to council by July 14.

MeetingJun 16, 2026

Board of Commissioners - Jun 16, 2026

New numbers on the latest judicial center proposal could land as early as next week; structural questions about putting big HVAC equipment in the old courthouse attic are being worked through.

MeetingJun 2, 2026

Board of Commissioners - Jun 2, 2026

Still no new numbers on the proposed judicial center — engineers are checking whether the courthouse roof structure can support new HVAC units, with figures expected around June 18.

MeetingMay 26, 2026

Board of Commissioners - May 26, 2026

Vendors walked through the old courthouse and cost estimates should land in a few weeks. Commissioners are weighing how much is new-project cost versus ongoing maintenance, and whether a $20 million referendum threshold applies.

MeetingMay 19, 2026

Board of Commissioners - May 19, 2026

The county is weighing a new concept: Superior Court moves into the historic courthouse, and a two-story annex across Third Street would house the clerk, prosecutor, probation, community corrections, and public defender. A walkthrough and cost estimate come next.

MeetingMay 6, 2026

Board of Commissioners - May 6, 2026

No decisions yet — the architect is working on a space plan that could move a superior court into the courthouse and build a new building across Third Street. Commissioners hope for a major decision within about a month.

MeetingApr 28, 2026

Board of Commissioners - Apr 28, 2026

County is still weighing moving Superior Court into the historic courthouse's first floor and building an annex across Third Street. Department heads and judges are trimming space asks to fit council's budget.

MeetingApr 14, 2026

Board of Commissioners - Apr 14, 2026

The big one: where do the courts and court-related offices go? A new $22M building was on the table, but a plan to keep both courts in the historic courthouse and build a smaller ~$14M office building across Third Street won the room. Final decision pushed past April.

MeetingApr 14, 2026

County Council - Apr 14, 2026

Commissioners and council are zeroing in on an $18-20 million judicial center — $8-10 million cash plus a ~$10 million loan paid from existing cash flow, with no tax increase. Anything above the state's ~$20 million threshold would force a public referendum, which couldn't happen until 2028.

MeetingMar 31, 2026

Board of Commissioners - Mar 31, 2026

Commissioners are weighing downtown Decatur versus the existing jail property for a new judicial center. Residents urged the jail site, saying downtown is landlocked and the veterans memorial must not be touched. No decision yet, but a downtown feasibility study is moving forward.

Decatur Daily DemocratMar 29, 2026

Many viewpoints given on still-indefinite plans for a “judicial center”

Many viewpoints given on still-indefinite plans for a “judicial center” Decatur Daily Democrat

MeetingMar 17, 2026

Board of Commissioners - Mar 17, 2026

The plan to renovate the Service Complex for the courts, probation and community corrections priced out at $19.5 million plus 25% soft costs — more than commissioners will spend. They're pivoting to a possible build-out at the county jail site, with Elevatus presenting a new plan next week. Downtown Decatur locations remain the preference if practical options appear.

MeetingMar 10, 2026

Board of Commissioners - Mar 10, 2026

The plan to move Superior Court, probation and community corrections into the service complex priced out around $20 million or more — way above what commissioners hoped. They're now looking at alternatives, including land they already own at the jail site.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Adams County

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.